October 29, 2025
The Bond Oversight Committee met on October 27 at Hughson High School for an update on Measure B projects and a tour of the completed projects. The committee’s role is to oversee whether the money is being spent as promised. It last met on May 5, 2025, and is required by law to meet once per year. Throughout the presentation, committee members had the opportunity to ask questions and make comments.
After a presentation on the numbers, schematics, and plans by Director of Maintenance, Operations, and Transportation Andrew Fontana, Hughson High School Principal Loren Lighthall led the committee on a tour of the new theater remodel and 40-wing, with new bathroom tile installed and a new classroom configuration.
The meeting began in Room 36 of the 30-Wing, giving committee members a first taste of the modernization.
The 30 Wing HVAC, 30 Wing Roof, 40-Wing Modernization, 10-Wing and 30 Wing Modernization, and asphalt are all in process. Work on the 30 Wing HVAC began on October 13. Estimated savings are $85,304.40.
The 30 Wing Roof replacement began on September 15. The original estimated cost was $745,264, and the actual cost was $305,418.16, saving the district $439,845.84. The reason for the large saving with this project, Fontana explained, is that the asbestos abatement required less work than anticipated. Both of these projects will finish this week.
The 10-Wing and 30-Wing Modernization, including asphalt, has a targeted start date of January 5, 2026, with an estimated completion date of July 31, 2026.
The tour began at the theater, one of the first projects completed under Measure B. The estimated cost of the Ella Webb Theater remodel including new theater seats, carpet and paint was estimated at $203,352. The final project was completed $29,276 under budget. At the time of the tour, theater seats were pushed back, and the space was set up for band class. While many committee members have seen the theater during plays, the tour offered the opportunity to see and discuss other ways the space is used for band and choir.
By exploring the footprint of the 40-wing, committee members voiced how the tour helps the project come to life for them. The 40 Wing Modernization began on August 13 and is estimated to be completed by December 31, 2025, although Fontana said the project's progress suggests it will likely be finished before Thanksgiving break. The interior of the building has been reconfigured into five classrooms, featuring new walls, flooring, efficient lighting, larger windows, and updated fixtures.
Looking at the bathrooms, many praised the tile design: clean, high-gloss ceramic white tile with a row of bright yellow horizontal tile between two black rows.
Superintendent Brenda Smith shared that the modernization project will include painting the entire campus and replacing the turquoise tiles on the gym to create a unified spirit and cohesive design. Where in old bathrooms tiles are falling from the ceiling, the new design is “super student friendly,” Hughson High School Principal Loren Lighthall said.
In the 40-wing, given the choice between four larger-than-necessary classrooms or five classrooms slightly smaller than the typical 950 sq ft, the district opted for five classrooms, knowing they could be used for special education classes, which typically have about 10 students. The smaller classroom seen by the committee includes an office space that can be used for IEPs.
The committee saw where portable housing will be installed in November. They discussed the choice to install and hook up portable buildings for the project. Given the multi-year nature of the project, leasing these structures made the most financial sense, Superintendent Brenda Smith explained. “This is a school, so we have to make sure we have great classroom spaces for our students. The staff has been really good about it,” she said. “This is going to go on for a couple of years, so we just wanted to make sure that we had adequate spacing.”
The Science Wing with Agriculture and Shop Complex project has been awarded to Boyer Construction. Construction is targeted to begin on June 8, 2026, and be hopefully completed on August 6, 2027.
Stadium upgrades are targeted to begin on December 1, 2026, with completion in August the following year.
The New District Office/MOT/AG Farm construction is targeted to begin on August 11, 2026, with completion on December 31, 2027. By moving the school district office from Ross Middle School and MOT from Hughson Elementary School, more space will be freed up for those schools to utilize existing buildings or add new classrooms.
Fontana continues to meet weekly with Boyer Construction, and he, along with the district team, meets weekly with the architect to keep all the pieces moving well and moving forward. Design and process questions still remain and are being finalized regarding the stadium upgrades and school farm. The team is weighing how to keep instructional opportunities in woodshop and welding during construction on the Agriculture building.
“It really has gone well. We're basically ahead of schedule and under budget. How often have you ever heard that on your own project, right?” Lighthall said. “For 46 million, man, I mean, I've been super pleased with it so far. So, it's gone very well.”
Thus far, projects are $554,425.56 under budget. Saved funds create a safety net for projects that may go over budget, asbestos abatement being a particular concern, and also open the door to more projects on the district’s list under the Bond Measure.
“The district is very thankful to the Hughson, Hickman, Gratton, and Roberts Ferry communities for passing Measure B,” Smith said. “These improvements will forever change Hughson High School's campus. Our students will benefit from their generosity for many years to come. We are excited to see the progression of the campus.”
The next meeting will be on May 4, 2026, at 3 p.m. Meetings are open to the public and utilize an agenda, which will be posted online prior to all meetings.



